Lam Trans Project Timeline

In November 2023, Electrical Technology management proposed building a new Lam board factory in Croatia to the Weidmann board board. The current Lam board production site in Ennenda, Switzerland, needs to be vacated by the end of June 2025; therefore, existing equipment must be transferred to Croatia, and for this purpose, Project LamTrans was initiated.

In Pojatno near Zagreb, close to the existing Weidmann facilities, a land plot of a total of 22,000 m2 was acquired to accommodate the new factory on a green field.

  • February 23, 2024
  • July 1, 2024
  • July 1, 2024
  • July 1, 2024
  • July 1, 2024
  • August 1, 2024
  • March 28, 2025
  • March 28, 2025
  • May 9, 2025
  • May 15, 2025
  • June 13, 2025
  • June 30, 2025
  • July 15, 2025
  • August 8, 2025
  • September 30, 2025
  • The building concept for the Pojatno site, including the layout for Production and Logistics, is completed

    During February and March 2024, the building concept was developed together with production and logistics experts.
  • Start of pre-production site Ennenda

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Proin pretium interdum odio pellentesque vestibulu
  • Start of pre-production site Malyn

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Proin pretium interdum odio pellentesque vestibulu
  • Start of pre-production site Rapperswil

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Proin pretium interdum odio pellentesque vestibulu
  • Building submission issue to authorities

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Proin pretium interdum odio pellentesque vestibulum.
  • Start building construction

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Proin pretium interdum odio pellentesque vestibulum.
  • Know-how transfer completed Ennenda->Pojatno

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Proin pretium interdum odio pellentesque vestibulum.
  • Preproduction completed site Ennenda

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Proin pretium interdum odio pellentesque vestibulum.
  • Eqipment disassembled, ready for transport (+1w)

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Proin pretium interdum odio pellentesque vestibulum.
  • Building release site Pojatno (+2w)

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Proin pretium interdum odio pellentesque vestibulum.
  • Equipment release for production start-up Pojatno (+2w)

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Proin pretium interdum odio pellentesque vestibulum.
  • Building handover site Ennenda

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Proin pretium interdum odio pellentesque vestibulum.
  • Internal release of production site Pojatno (+2w)

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Proin pretium interdum odio pellentesque vestibulum.
  • Customer audits completed site Pojatno (+1w)

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Proin pretium interdum odio pellentesque vestibulum.
  • Customer release site Pojatno

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Proin pretium interdum odio pellentesque vestibulum.