The building concept for the Pojatno site, including the layout for Production and Logistics, has been completed

During February and March 2024, the building concept was developed together with production and logistics experts. On March 18th the steering committee decides for building version of total 7200m2 surface. The planning contains production, warehouse and offices.

The building concept for the Pojatno site, including the layout for Production and Logistics, has been completed

Preproduction of additional 1’500 tons LamBord started July 24 to cover planned customer demand during the transition phase. Preproduction is packed in double layer packaging and stored in defined locations.

Building submission issue to authorities

Architects main design was finished July 24 and project was submitted to local authorities for building permit. The building is designed to meet state of the art levels of sustainable energy management and environmental protection.

Start building construction

Construction on site started with ground preparing works. Beginning of October we obtained official building permit and started to erect the building. Construction makes fast progress as it mainly contains prefabricated elements.